Start Date Project Milestone Description
October 2003 Project Started
January 2004 Development Hardware Installed
January 2004 Main UNO Training Lab Completed in CP141
January 2004 Luminis Portal/CMS Gathering
January 2004 Test installation of Luminis Portal
January 2004 General Person Data Standards Training
February 2004 Lumins Portal Content and Organizational Planning Sessions
February 2004 Cognos Installation
March 2004 2nd UNO Training Lab completed in ARC A 106D
March 2004 Cognos Report Net Training
March 2004 Operational Data Store Technical Training
April 2004 Advancement Kick Off
April 2004 General Consulting and Testing
May 2004 Luminis Trainer Certification Training
May 2004 End User Training Lab in ARC A Room 101
June 2004 Data Conversion for HR completed
August 2004 Interfaces for HR completed
September 2004 Banner Recruitment and Admissions Upgrade to 6.1 and Oracle 9i and Implementation of Self Service
October 2004 Critical Reports for HR completed
October 2004 General Navigation Training
October 2004 Matrix Kick Off
October 2004 Core Team Training for HR
December 2004 HR End User Training
November 2004 Parallel Payroll Runs (new system/old system)
November 2004 Project work space in Milton
December 2004 Develop Maps to New Models (Data Mapping)
December 2004 Go Live for E-Hire
December 2004 Web Time Entry and E-Hire End User Training
December 2004 Convert to new email system
December 2004 Establish or verify NMSU Username and Password through accounts.nmsu.edu
December 2004 Migrate data of PIN to new server
December 2004 Export aliases to Luminis (myNMSU)
January 2005 Non Critical Reports for HR completed
January 2005 Go Live for Banner HR
January 2005 Go Live for Luminis
April 2005 Move NMSU Phonebook to new server
May 2005 Cognos Core Team Training
May 2005 Oracle Upgrade to 9.2.0.5
May 2005 Finance End User Training
May 2005 Finance Self Service Overview: Sessions
June 2005 Interfaces for Finance Complete
June 2005 Data Conversion for Finance Complete
July 2005 Go Live for Finance
July 2005 Go Live for Content Management System
September 2005 Banner Recruitment and Admissions Merge with ERP Banner